City Subscriptions

View Press Release

FOR IMMEDIATE RELEASE
City of Duluth Communications Office
Mayor Roger J. Reinert
411 West First Street • Duluth, Minnesota 55802 • www.duluthmn.gov
For more information, please call 218-730-5309
DATE: 7/8/2020
SUBJECT: Superior Street Reconstruction Update: Word on the Street (July 8, 2020)
BY: Kate Van Daele, Public Information Officer

  Superior Street Reconstruction Update: Word on the Street (July 8, 2020)

Wrap-up of Last Week

  • Crews continued grading, forming and pouring sidewalk and roadway at Lake Avenue. 
  • Carpentry crews worked on the east plaza at Lake Avenue.  
  • Pipefitters continued installing the hot water lines in 1st Avenue West. 
  • Workers made connections from the old storm sewer system to the new storm sewer system in 1st Avenue West.
  • Electrical duct banks were built from Lake to 1st Avenue West.
  • Crews removed bricks, paving and ledge rock to prepare for the steam removal.
  • Removal of the of 100 year steam heating system restarted from 2nd to 3rd Avenue West. The removal of the existing District Steam Heating System, within the limits of this year’s project, involves the mitigation and removal of the existing asbestos containing steam pipes that have been serving Downtown Duluth for over 100 years. The removal of these pipes will be performed by a licensed asbestos abatement contractor and environmental monitoring will be performed to ensure worker and public safety. Signs will be placed at the location of the work site to inform the public that asbestos abatement is occurring and to delineate the work zone. Public cooperation is requested to stay within the designated pedestrian areas and out of the delineated work zone. Access to all businesses will be maintained while this work is performed.

What to Expect July 8 - 14

  • Access to businesses and residences will remain open.
  • Bricks, pavement and ledge rock will continue to be removed throughout the project zone.
  • Crews will pour roadway and sidewalk on the upper side of Lake Avenue as well as bridge approach panel on the south side.
  • Structural work on vaults will continue.
  • Permanent water and storm sewer tie-ins will begin between from 1st Avenue West and 2nd Avenue West.
  • Hot water installation will continue from in 1st Avenue West.
  • Storm structure work will continue in 1st Avenue West.
  • Beginning Friday, July 10 through the weekend, Michigan Street at 2nd Avenue West will be closed for critical utility tie-in work.
  • Beginning Monday, July 13, the alley at 2nd Avenue West between Superior Street and 1st Street will be closed to perform utility upgrades.

 

Lake Avenue Update

  • For questions on the Lake Avenue Bridge project please contact Margie Nelson, MnDOT Public Affairs Coordinator District 1, O: 218-725-2708, Margaret.nelson@state.mn.us

Weekly Meeting

  • Weekly construction meetings will be held on Tuesdays at 10:00am. To accommodate public meetings, community members may use the following conference line until group gathering restrictions have been lifted.
    • +1 651-964-6935   United States, St. Paul (Toll)  Conference ID: 289 046 099#

Parking Ramps             

  • Many ramps are offering free parking if you enter and leave within an hour.  For those accessing businesses in the construction zone, the following ramps are participating:
    • Civic Center Ramp—410 West First Street
    • Tech Village Ramp—10 East First Street
    • Duluth Transportation Center—228 West Michigan Street
    • 4th Avenue Auto Park—402 West Michigan Street
    • Hart District Ramp—125 East Superior Street
    • Medical District Ramp—302 East First Street